Repair of collapsed Side Wall

The
Callout

Fuse Tech was called by customer end of March 2017 because side wall starts falling in.

The
Solution

Carry out
the job

Working day 1 – day shift:

Fuse Tech team started the works with exchange of the collapsed wall

Working day 1 – night shift:
Working day 2 – day shift:
End of working day 2 – night shift:
Working day 3 – day shift:

After 3 days the collapsed side wall was exchanged.

The
Result

After hotface-welding 2017

Proof / History

Situation November 2017:
Situation November 2018:
Situation April 2019:

After this picture the furnace was stopped end of April 2019.